Conduit holes were cut in CS6, 7 and center bulkheads.  The holes will be in the bottom corner rather than right through the center so cables will lay flatter.   The holes are large enough that I microed some 1" long 1" NEMA conduit into the holes.   Added about one ounce total for the 3 conduit bushings.  

The CS4 panels were ready to put on but I spent literally hours going over Figure 4 and measurements on pages 5,6 & 7.   I pinged another builder regarding my apprehension about where exactly the CS5 & 8 bulkheads mount.   It appears on some builders pages, they attached the end bulkheads onto the end of CS1,2 & 3 without trimming 1/4" to mount CS5 & 8 flush with the jig.


I held off on microing the CS4 parts on since its supposed to get cold again.   I'd like to get better ventilation in the room where I'm working as I've noticed the smell of the hardener accumulates.   I'll plan on relocating the pump to an enclosed/heated station.  

We'll have guests soon for the Christmas, so I'll concentrate on some tasks that need to be done in the shop that will help with project construction later.




No comments:

Post a Comment